Vermont utility makes wind power a local priority

Published Wednesday, 7th September 2011

Vermont’s Green Mountain Power has begun building a new wind-energy project that will generate enough power for more than 24,000 homes.

The 21-turbine, 63-megawatt (MW) Kingdom Community Wind project in Lowell will produce electricity for Green Mountain Power customers and members of the Vermont Electric Coop.

Even before construction has started, the project has generated payoffs for the regional economy. More than 90 different Vermont firms and vendors have participated in the project to date, with more than $4 million already invested in those companies. In the coming weeks, contractors — including Vermont-based contractors like J.A. McDonald of Lyndon Center and Bates & Murray of Barre — expect to add more local employees to their existing base to work on the wind farm.

“This is a local energy project built by Vermonters, for Vermonters,” said Mary Powell, president and CEO of Green Mountain Power (GMP). “Through tax payments to the town of Lowell, the state education fund, the Good Neighbor Fund for surrounding towns and the economic activity created by the project’s construction, as well as competitively priced energy for many years to come, this project is a true win-win for all involved.”

Construction of the wind farm actually encompasses two projects. First comes the installation of the turbines themselves, which is expected to be completed by the end of 2012. The second project involves upgrades to the Vermont Electric Coop’s transmission system.

“Our 40-year-old transmission system between Lowell and Jay needed to be upgraded to ensure safety and reliability,” said David Hallquist, CEO of the Vermont Electric Coop. “Our members have also told us that they want clean, local and affordable electricity. Our partnership with GMP on this renewable wind project will help us meet those requests in a way that keeps rates as low as possible.”

In July, members of the cooperative voted to support the transmission system upgrades, with nearly 80 percent in favor. The Kingdom Community Wind project also won the approval of Lowell voters at a 2010 Town Meeting Day ballot, with three out of four voters signalling their support.

Kingdom Community Wind received a certificate of public good (CPG) from the Vermont Public Service Board in late May. GMP has now met all the pre-construction conditions in the CPG and received all of the permits required to begin construction, including permits related to protecting water quality that were issued late August.

During and after construction, there will also be biological monitoring of streams — a first for either wind or ski areas in Vermont.

Upon completion, the wind farm will qualify for about $47 million in federal production tax credit that will go entirely to lowering the cost of energy for Green Mountain Power customers and Vermont Electric Coop members.

Bookmark and share:
  • Twitter
  • Google Bookmarks
  • LinkedIn
  • Facebook
  • Reddit
  • StumbleUpon
  • Digg
  • Slashdot
  • del.icio.us
  • email
  • Print
  • PDF











RELATED NEWS

Latest Insight

Germany’s no-nukes plan leads to gas pains thumbnail

Germany’s no-nukes plan leads to gas pains

Germany’s already an undisputed powerhouse in renewable energy, but it will need to
Which countries produce the most wind energy? thumbnail

Which countries produce the most wind energy?

The world was producing nearly 238 gigawatts (GW) of wind energy as of
China ‘dumping’ low-cost solar cells on market? US says ‘yes’ thumbnail

China ‘dumping’ low-cost solar cells on market? US says ‘yes’

Have China’s solar cell makers been “dumping” their products on the US market

LATEST REPORTS
1

Who’s the leading smart-city brand?

More than half of the world’s nearly seven billion people now live in urban areas, and that proportion is expected to reach almost 69 per cent by 2050. To avoid pushing local and global systems to the point of collapse, cities will need to become much smarter and more efficient Read more ...
more info
2

Managing the smart-grid data overload

Developing the UK’s smart-grid infrastructure will require communications and data technologies that can manage far more information than utilities must handle today. That’s the focus of a strategy report from Greenbang Research: “Enabling the UK’s smart-grid future: The wireless spectrum debate.” The report answers such questions as: Should dedicated Read more ...
more info
3

Incentives fire up UK solar market

The introduction of the feed-in tariff (FIT) incentive policy on 1 April has sparked an explosive reaction in the UK renewable energy market with solar leading the way in installations, according to a new Greenbang research report titled, “The UK’s Feed-in Tariff: Impact, response and market trends for the decade Read more ...
more info